North McKinnon & Centre Road Level Crossing Removal Project
Client
John Holland
Year
2016
Location
Melbourne, Australia
About the project:
Tunnelling Solutions supplied specialised shotcrete supervisors to John Holland for the Level Crossing Removal Project in Melbourne.
Project snapshot:
- The project was tasked to apply 5600m3 of shotcrete during a 37 day shut down period to the North, McKinnon and Centre Road Stations.
Completed work:
- With a variety of shotcrete sub-contractors from across the country, Tunnelling Solutions collaboratively lead the team to a successful result and with the work completed on time.