NEPA Darebin Rail UnderPass
Client
Year
Location
About the project:
Our team completed the Darebin Rail Underpass (under Darebin Road and Hawdon Street in Heidelberg, Melbourne) for the North East Program Alliance – which included Laing O’Rourke, Fulton Hogan, Jacobs, Metro Trains Melbourne and Level Crossing Authority.
Project snapshot:
- The construction of an adjacent tunnel next to an existing rail tunnel built in 1912 was provided as a design and construct solution for our client.
- Total length of the underpass is 70m.
Completed work:
- Differing support types were used to address low cover and proximity to critical services including gas main, water main and various telecommunications.
- Support of works included a combination of steel ribs with shotcrete, spile bars, rock bolts, soil nails, and canopy tubes (DN300mm – 9 no. each 36m long).
- Tunnel construction was completed tunnel construction on time with no disruption to the existing rail line and zero settlement recorded on surrounding roads.
Tunnelling Solutions successfully completed the design and construction of a 70 metre tunnel for the North East Program Alliance. The works were carried out adjacent to a live railway and alongside an existing brick tunnel constructed in the early 1900’s. Their involvement within the early works of the project was invaluable resulting in a design which was constructible and optimised for the ground conditions at hand. The works involved a heading and benching methodology to minimise disturbance to the adjacent tunnel and jacking a series of ~300mm canopy tubes, each approximately 36m long, to enable the support of the crown of the tunnel directly underneath sensitive services such as gas and water. The works were carried out professionally and collaboratively throughout and I would gladly recommend Tunnelling Solutions for any future works.
Con Anagnos Project Manager