Tunnelling Solutions recently supplied specialised shotcrete supervisors to John Holland for their Level Crossing Removal Project in Melbourne. 

The project was tasked to apply 5600m3 of shotcrete during a 37 day shut down period to the North, McKinnon and Centre Road Stations.  With a variety of shotcrete sub-contractors from across the country, Tunnelling Solutions collaboratively lead the team to a successful result and with the work completed on time.

For more information on this project, go to